Trial Runs Begin at New Toll Plaza Near Uppinangadi
The newly built toll plaza near Valalu in Bajatturu village, about eight kilometres from Uppinangadi, has opened for trial runs, highway officials said on Tuesday. Completion of the structure follows the finalisation of the four‑lane concrete road project that links B.C. Road with Addhole.
Contractor K.N.R. Construction finished the toll gate and handed it over to the National Highway Authority, which is expected to issue an official notification within the week. Once the notice is released, toll collection will commence.
The four‑lane highway segment between B.C. Road and Periyashanti, spanning 46 kilometres, is already 95 per cent complete. Each direction carries four lanes, allowing a total of eight lanes for uninterrupted traffic. Separate lanes have been set aside for two‑wheelers and auto‑rickshaws, and two of the eight lanes will serve cash‑plus Fast Tag users while the remaining six lanes are dedicated to Fast Tag only, with payments accepted via phone‑pay, Google Pay or QR‑code scanning.
Coral, a Mangalore‑based firm, secured the toll‑collection contract after the tender process concluded. Vehicles registered in Dakshina Kannada will enjoy a fifty per cent discount, and residents living within a twenty‑kilometre radius of the plaza can purchase a monthly pass for Rs 360.
According to Yajnesh, an administrative partner at Coral, the new plaza will be the second on the Bangalore‑Mangalore stretch of National Highway 75, joining existing plazas at Brahmarakutlu and five others between Bangalore and Sakaleshpur. The addition will raise the total to seven toll points on the route.
RTI activist Shabeer Ahmad Nekkilaadi highlighted that the distance between the Brahmarakutlu plaza and the new Valalu gate is only thirty‑eight kilometres, whereas highway guidelines recommend a minimum spacing of sixty kilometres. He warned that the short interval could inconvenience commuters.
Image: varthabharati.in
📰 Source: Vartha Bharati DK